Microsoft MB5-858 Exam Overview:
| Certification Vendor: | Microsoft |
|---|---|
| Exam Name: | Managing Microsoft Dynamics Implementations |
| Exam Number: | MB5-858 |
| Exam Duration: | 120–140 |
| Exam Format: | Scenario-Based, Case Study, Multiple Choice |
| Passing Score: | 700 / 1000 |
| Available Languages: | English |
| Certificate Validity Period: | Retired since October 1, 2011; no longer valid or renewable |
| Real Exam Qty: | 65–75 |
| Exam Price: | $99 USD |
| Related Certifications: | Microsoft Certified Business Management Solutions Professional Microsoft Dynamics Sure Step Methodology |
| Recommended Training: | Microsoft Dynamics Sure Step Training |
| Exam Registration: | Prometric (Historical) |
| Sample Questions: | ![]() |
| Exam Way: | Proctored via Prometric test centers; retired |
| Pre Condition: | No formal prerequisites; recommended experience in Microsoft Dynamics projects and Sure Step methodology |
| Official Syllabus URL: | https://learn.microsoft.com/en-us/archive/blogs/auspartnertraining/sign-up-now-to-prepare-for-the-mpn-implementation-methodology-exam-prometric-exam-mb5-858-before-1-oct-deadline |
Microsoft MB5-858 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Prepare to Manage a Microsoft Dynamics Implementation | 47% | - Understand Microsoft Dynamics Sure Step methodology - Define project scope and charter - Identify stakeholders and governance structure - Estimate resources, budget, and timeline |
| Post-Implementation & Cross-Phase Management | 12% | - Operation and support handover - Risk and change management - Tollgate reviews and project closure - Communication and training |
| Manage Implementation Lifecycle | 41% | - Analysis and design phase deliverables - Development and configuration - Testing and quality assurance - Deployment and go-live - Diagnostic phase activities |
Your MB5-858 Exam Questions Answered
Microsoft recommends these training resources for the Microsoft Managing Microsoft Dynamics Implementations exam:
Follow the training with steady self-testing — the 109 practice questions from TorrentExam help you apply theory and fill any gaps the training leaves.
The Microsoft Managing Microsoft Dynamics Implementations exam contains 65–75 to complete within 120–140. Timed simulation in the TorrentExam Desktop Test Engine teaches that rhythm before exam day does.
The official Microsoft Managing Microsoft Dynamics Implementations outline defines 3 domains. The leading three are Manage Implementation Lifecycle (41%), Post-Implementation & Cross-Phase Management (12%), and Prepare to Manage a Microsoft Dynamics Implementation (47%). The full list is in the topics section above, and TorrentExam's 109 practice questions cover each one.
The MB5-858 exam is a Microsoft certification exam validating the Microsoft Managing Microsoft Dynamics Implementations syllabus shown above. It belongs to these credential paths: Microsoft Dynamics Sure Step Methodology, Microsoft Certified Business Management Solutions Professional. Earning the credential in 2026 can strengthen a career, and TorrentExam prepares candidates with 109 practice questions in PDF, Desktop Test Engine, and Online Test Engine formats.
Proctored via Prometric test centers; retired Register for the Microsoft Managing Microsoft Dynamics Implementations exam through these official channels:
After booking, TorrentExam delivers your practice questions within 1 minute — preparation starts the same day.
The Microsoft Managing Microsoft Dynamics Implementations exam requires 700 / 1000 to pass, and registration costs $99 USD. A failed attempt means paying the same fee again — a readiness check with the TorrentExam engines before booking is the cheaper option.
Three versions of the same study materials: a printable, expert-prepared PDF with free demo download and instant access; a Desktop Test Engine for Windows that simulates the real exam with two practice modes and works offline; and an Online Test Engine for any browser on Windows, Mac, Android, and iOS with test history and performance review. Download the demo first, experience the materials, and choose the format you like best — all 109 practice questions are identical across versions. Every purchase includes 365 days of free updates, a 50% renewal discount afterward, and unlimited computer installations.
TorrentExam issues a full refund if you take the Microsoft Managing Microsoft Dynamics Implementations exam within 60 days of purchase and do not pass. The policy does not apply if the exam is taken within 3 days of purchase, if the exam was never actually taken, or to free materials or expired orders, and the candidate name must match the payer name. Submit a scan of your enrollment slip and the official Score Report PDF within 2 days of the exam; claims are processed within 7 days. Alternatively, exchange for two free exam products of equal value and keep your original update service. Orders arrive by email within 1 minute — contact support if nothing arrives within 2 hours.
No formal prerequisites; recommended experience in Microsoft Dynamics projects and Sure Step methodology Since requirements change over time, confirm the latest on the official Microsoft exam page before scheduling.
Microsoft Managing Microsoft Dynamics Implementations Sample Questions:
You are determining the contract type for a new engagement. Based on the available diagnostic information, you come to the following conclusions:
-
There is uncertainty about a majority of the requirements
-
There is a significant gap between a large set of requirements and your Microsoft Dynamics solution
-
Your project team is not familiar with the customers's industry
-
Your customer is not familiar with implementation projects and business software.
Which contract type should you recommend?
- A. Fixed price
- B. Time and Material
- C. Estimate for Analysis and Design, Fixed Price for Development and Deployment
- D. Fixed Price for Analysis and Design, Estimate for Development and Deployment
Correct Answer: B 🗳️
Your team is implementing a Microsoft Dynamics solution by using an Agile Project Type approach. Your customer wants to be able to quickly change the direction of solution development to adapt to changed business procedures.
How can you meet this customer need?
- A. By organizing weekly sprint cycle meetings.
- B. By organizing monthly review meetings.
- C. By providing a project status report on a weekly basis.
- D. By organizing daily sprint cycle meetings
Correct Answer: D 🗳️
The development consultants are documenting the user interface, business and data layer components that will be required to deliver each proposed system modification. They are also reviewing the design security and identifying additional security requirements.
What are they doing?
- A. Identifying process testing scenarios
- B. Creating the solution design document, including all solution design elements for presentation and eventual sign-off by the customer.
- C. Creating the technical design document for the proposed system modification.
- D. Creating the gap design in the functional design document.
Correct Answer: C 🗳️
Your company is preparing a proposal for a large and complex implementation that will require significant customizations in an enterprise organization. One of the elements that you plan to address is testing and creating a test plan. When is the best time to create a high-level test plan that includes the general standards and procedures that must be followed when conducting software testing and validation?
- A. After design specifications are finalized.
- B. During project scoping and planning in the Analysis phase.
- C. During the beginning of the deployment phase.
- D. During the custom code activity.
Correct Answer: B 🗳️
Your project manager is verifying that all acceptance criteria have been met and confirming that final technical and management reviews of deliverables are complete. The project manager is also collecting intellectual property and confirming that service plans have been delivered to the customer.
What is your project manager doing?
- A. Closing a phase by means of a tollgate review document.
- B. Preparing for the upcoming project by means of a Project Charter.
- C. Preparing for project closure by means of an engagement closure checklist.
- D. Executing a risk assessment by means of a risk register.
Correct Answer: C 🗳️