PRINCE2 PRINCE2-7-Practitioner Exam Overview:
| Certification Vendor: | PeopleCert |
|---|---|
| Exam Name: | PRINCE2 Project Management Practitioner (Version 7) |
| Exam Number: | PRINCE2-7-Practitioner |
| Passing Score: | 60% (42 out of 70 marks) |
| Exam Price: | US$778.00 (exam voucher + Learning Resource Kit, including VAT; country-specific pricing may vary) |
| Real Exam Qty: | 56 questions and sub-questions (70 marks total) |
| Exam Format: | Objective Testing, Open Book, Scenario-based questions, Computer-based examination |
| Certificate Validity Period: | 3 years; certification is subject to renewal, with 60 CPD points required for renewal |
| Related Certifications: | Project Professional Qualification (PPQ) IPMA Level B (Certified Senior Project Manager) PRINCE2 5th Edition Foundation IPMA Level A (Certified Projects Director) IPMA Level C (Certified Project Manager) IPMA Level D (Certified Project Management Associate) Certified Associate in Project Management (CAPM) PRINCE2 5th Edition Practitioner Project Management Qualification (PMQ) PRINCE2 Project Management Foundation (Version 7) Project Management Professional (PMP) PRINCE2 6th Edition Foundation PRINCE2 6th Edition Practitioner |
| Exam Duration: | 150 minutes |
| Available Languages: | Chinese, Portuguese (Brazil), Czech, Danish, Norwegian, English, Japanese, Dutch, French, Slovak, German, Italian, Polish, Spanish |
| Sample Questions: | ![]() |
| Exam Way: | Online proctored examination from home or office; PeopleCert also supports examination through accredited training organizations and test-center arrangements. |
| Pre Condition: | Prerequisite required. Candidates must hold one of the accepted certifications, including PRINCE2 Project Management Foundation (Version 7), PRINCE2 6th Edition Foundation or Practitioner, PRINCE2 5th Edition Foundation or Practitioner, PMP, CAPM, PPQ, PMQ, IPMA Level A, B, C or D, or other PeopleCert-approved equivalent qualifications. |
| Official Syllabus URL: | https://www.peoplecert.org/browse-certifications/project-programme-and-portfolio-management/PRINCE2-2/PRINCE2-7-practitioner-3581 |
PRINCE2 PRINCE2-7-Practitioner Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| People | - Leading successful change - Effective communication - Leading successful teams |
| PRINCE2 Project Management Processes | - Starting up a project - Managing product delivery - Managing a stage boundary - Controlling a stage - Directing a project - Closing a project - Initiating a project |
| PRINCE2 Project Management Practices | - Business case - Issues - Quality - Progress - Organizing - Plans - Risk |
| Project Context and Tailoring | - Delivery methods and approaches - Commercial context - Digital and data management - Organizational context - Sustainability - Project scale and complexity - Tailoring PRINCE2 to the project context |
| PRINCE2 Project Management Principles | - Learn from experience - Ensure continued business justification - Tailor to suit the project - Focus on products - Manage by exception - Define roles, responsibilities and relationships - Manage by stages |
PRINCE2-7-Practitioner Exam Essentials: Format, Topics, and Policies
The current exam information lists 56 questions and sub-questions (70 marks total) questions for the PRINCE2-7-Practitioner exam, with 150 minutes minutes allowed. Practicing against the clock at home builds the pacing habits that exam day rewards.
The PRINCE2 Project Management Practitioner (Version 7) blueprint covers these main domains:
- PRINCE2 Project Management Processes
- PRINCE2 Project Management Practices
- Project Context and Tailoring
Additional domains complete the official outline, and our bank covers the full range.
Your money is protected by clear conditions. If you fail the corresponding exam within 60 days of purchase, send us a scanned copy of your enrollment slip and your official Score Report PDF within two days of the exam date; verified claims receive a full refund within seven days. The exclusions: exams taken within three days of purchase, a candidate name that does not match the payer, and free or expired products. If you prefer, we can exchange your product for two others of equal value instead.
PRINCE2 lists the following prerequisites for the PRINCE2 Project Management Practitioner (Version 7): Prerequisite required. Candidates must hold one of the accepted certifications, including PRINCE2 Project Management Foundation (Version 7), PRINCE2 6th Edition Foundation or Practitioner, PRINCE2 5th Edition Foundation or Practitioner, PMP, CAPM, PPQ, PMQ, IPMA Level A, B, C or D, or other PeopleCert-approved equivalent qualifications..
Check the official certification page for the latest requirements before booking.
Because we remove the guesswork at every step. The PRINCE2-7-Practitioner bank consolidates the PRINCE2 Project Management Practitioner (Version 7) knowledge points into expert-verified Q&As instead of leaving you to sift through the internet alone. A free demo shows the quality before you buy; instant delivery starts you the minute you do; 365 days of free updates — with a notification each time a new version releases — keep you current; and a strict information safety system plus a 7/24 golden-standard support team protect you throughout.
As of the latest information, the PRINCE2-7-Practitioner exam requires a score of 60% (42 out of 70 marks) to pass, and registration costs US$778.00 (exam voucher + Learning Resource Kit, including VAT; country-specific pricing may vary). PRINCE2 sets both figures, so verify them on the official site when you book.
Upon successful payment, our system automatically emails the product to your mailbox and shows an instant download link — delivery typically takes about a minute. If nothing arrives within two hours, check your spam folder first, then contact our 7/24 support team. Installations are unlimited. Your purchase also includes 365 days of free updates: whenever we release a new version, we notify you to download it — no need to wait or worry about validity — and a 50% renewal discount applies when the period ends.
PRINCE2 Project Management Practitioner (Version 7) Sample Questions:
During the 'initiating a project' process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
- A. No, because early identification of an opposing group will necessarily increase its opposition
- B. Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively
- C. No, because stakeholder identification should not take place during project initiation
- D. Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case
Correct Answer: B 🗳️
Explanation: Only visible for TorrentExam members. You can sign-up / login (it's free).
At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.
Is this an appropriate application of the 'manage by stages' principle, and why?
- A. No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance
- B. Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight
- C. Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions
- D. No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project
Correct Answer: A 🗳️
Explanation: Only visible for TorrentExam members. You can sign-up / login (it's free).
PROGRESS
Here are three actions related to the 'progress' practice for the LouisShopping project.
Which role (A-E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
- A. Team manager
- B. Project assurance
- C. Project executive
- D. Project manager
- E. Project support
Action 1:
Assist the project manager in compiling the lessons report, including the recommendation that future projects allow more time for testing and inspections.
Action 2:
When delays to the floor installation cause the stage to be forecast beyond tolerance, submit an exception report to the project board for a decision.
Action 3:
Review the exception plan and decide whether to approve it, including the revised stage targets and tolerances.
Correct Answer: C,D,E 🗳️
Explanation: Only visible for TorrentExam members. You can sign-up / login (it's free).
BUSINESS CASE
Here are three statements related to the 'business case' practice.
In which management product should each statement be recorded?
Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.
- A. Sustainability management approach
- B. Project brief
- C. Commercial management approach
Statement 1:
The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.
Statement 2:
One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles.
The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will review the resulting data to determine whether the target has been achieved.
Statement 3:
The City Council has committed the funding for the LouisShopping investment through the Louistown is Open for Business portfolio. - D. End stage report
- E. Business case
- F. Benefits management approach
Correct Answer: C,E,F 🗳️
Explanation: Only visible for TorrentExam members. You can sign-up / login (it's free).
The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.
Is this an appropriate application of the quality practice, and why?
- A. No, because assurance information may be provided to the project board and not to the business layer
- B. Yes, because the portfolio office should manage the project's quality-control activities on behalf of the project manager
- C. No, because a portfolio office may assess strategy but may not review the delivery of individual projects
- D. Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf
Correct Answer: D 🗳️
Explanation: Only visible for TorrentExam members. You can sign-up / login (it's free).
Viewing page 1 out of 12 pages.
Viewing questions 1-5 out of 58 questions.