Good preparation pays off fast. Work through the CompTIA Project+ questions from TorrentExam — 96 of them — and watch mock scores climb long before PK0-400 test day.
CompTIA PK0-400 Exam Overview:
| Certification Vendor: | CompTIA |
|---|---|
| Exam Name: | CompTIA Project+ |
| Exam Number: | PK0-400 |
| Available Languages: | English, Japanese |
| Exam Duration: | 90 minutes |
| Exam Format: | Multiple Response, Multiple Choice, Scenario-Based Questions |
| Real Exam Qty: | Maximum 95 |
| Exam Price: | USD 285 |
| Certificate Validity Period: | Lifetime (Good-for-Life certification) |
| Related Certifications: | CompTIA Project+ Certification |
| Passing Score: | 710 (on a scale of 100-900) |
| Sample Questions: | ![]() |
| Exam Way: | Pearson VUE test centers or online remote proctored exam. |
| Pre Condition: | No prerequisite exam required. Recommended: at least one year of experience managing, directing, or participating in small- to medium-scale projects. |
| Official Syllabus URL: | https://www.comptia.org/certifications/project |
CompTIA PK0-400 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Project Constraints | 17% | - Risk Management
|
| Project Tools and Documentation | 21% | - Project Management Tools
|
| Communication and Change Management | 26% | - Project Communications
|
| Project Basics | 36% | - Cost and Resource Management
|
PK0-400 Essentials — FAQ
Delivery takes about a minute: successful payment triggers an automatic email with your files, installable on unlimited devices — contact our 24/7 staff if nothing arrives within 2 hours (check spam first). And a failed attempt doesn't leave you stranded: take the corresponding PK0-400 exam within 60 days of purchase, submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam, and we process a full refund within 7 days. Excluded: exams within 3 days of purchase, payer-name mismatches, and free or expired products. Alternatively, switch to two other equal-value products free.
Expect USD 285 per attempt and a passing score of 710 (on a scale of 100-900). A retake costs the full fee again — one more reason to rehearse with the 96 practice questions from TorrentExam until your mock scores sit comfortably above the mark.
The CompTIA Project+ blueprint covers 4 domains — including Project Basics (36%), Project Constraints (17%), Communication and Change Management (26%). Let the weightings steer your schedule: the heavier the domain, the heavier your practice time. Every subtopic is listed in the outline above.
No prerequisite exam required. Recommended: at least one year of experience managing, directing, or participating in small- to medium-scale projects. Since vendors update eligibility rules periodically, verify the current requirements on the official page (official PK0-400 exam page) before registering.
The CompTIA Project+ is CompTIA's official exam for the CompTIA Project+ credential (Professional level). Passing it certifies a professional background that helps you stand out at work instead of running with the crowd. It also relates to CompTIA Project+ Certification.
90 minutes for Maximum 95 questions. Effective review beats anxious cramming: rehearse timed sets in the TorrentExam engine until pacing becomes habit, and the clock becomes an asset instead of a threat.
Yes — the free CompTIA Project+ demo shows real question quality before you pay, the surest way to identify helpful material in a crowded market. Buying includes 365 days of free updates, renewable later at 50% off.
CompTIA Project+ Sample Questions:
Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
- A. Product item
- B. Team lead
- C. Sales clerk
- D. Marketing representative
Correct Answer: D 🗳️
The PMO is responsible for: (Choose two.)
- A. setting standards and practices for the organization and providing governance.
- B. managing the project plan, scope, risk, and budget.
- C. outlining consequences of non-performance and coordinating between disparate projects.
- D. contributing expertise, deliverables, and estimates of costs.
- E. approving funding, developing the project schedule, and gathering high-level requirements.
Correct Answer: A,C 🗳️
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
- A. Total project cost
- B. Cost baseline
- C. Cost variance report
- D. Burn rate
Correct Answer: B 🗳️
Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
- A. Budget baseline
- B. SCRUM retrospective
- C. Kickoff meeting
- D. Risk review
Correct Answer: B 🗳️
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?
- A. Avoidance
- B. Acceptance
- C. Mitigation
- D. Exploitation
Correct Answer: D 🗳️
Viewing page 1 out of 20 pages.